Google’s $15b India data centre project battles water, wildlife concerns

Table of Contents

Activists, children march with banners reading ‘We cannot drink DATA’ in Visakhapatnam

A truck at the construction site of the Google-Adani data centre in Tarluvada, Visakhapatnam, Andhra Pradesh, India. Photo: Reuters

Work to build Google’s planned Indian data centre hub is in full swing, with a ​hillside above the site stripped to red earth and terraced into steps, but mounting opposition from environmentalists is creating hurdles for the US tech ‌giant’s $15 billion project.

The southern state of Andhra Pradesh, governed by an ally of Prime Minister Narendra Modi who has hailed the project as historic and transformational, has denied allegations that the project was fast-tracked without weighing risks to water supplies and wildlife.

But the growing opposition could become an early test for Google’s biggest-ever India investment, which is facing several legal challenges over its impact on water ​supplies and proximity to a wildlife sanctuary that is home to leopards and pangolins.

In recent weeks, activists and children have marched in Visakhapatnam city, holding ​banners saying “We cannot drink DATA” and painting handcuffs on the Google logo, social media posts show.

On Sunday, Reuters attended a public ⁠gathering where activists chalked out plans for holding door-to-door awareness campaigns and beach protests in the coming days.

“Development should not be at the cost of the livelihood of the ​people,” Raja Rama Mohan Roy, founder of non-profit Green Visakha, said at the event where he presented statistics on Visakhapatnam’s stressed water supply and demand.

Read: Google appeals Indian ruling over its ads platform, citing consumer harm

The government says the city ​receives 410 million litres of water a day from its reservoirs and rivers, against a requirement of 480 million. Rationing of water supplies is common in the city with a population of 2.5 million people.

Rapid data centre buildouts are facing pushback around the world for using huge quantities of water to cool servers and electricity. The potential impact is even more pronounced in a ​developing nation like India. In the US, opponents held 142 protests across 42 states in July, raising similar concerns.

State defends, open to redressal

The state’s top court on Monday ​asked the government to defend against allegations levelled by activist group Jal Biradari (Water Community), which says the project will strain water availability by putting stress on a nearby reservoir.

The Andhra Pradesh High ‌Court will ⁠next hear the public interest litigation on August 24.

The state, in its statement to Reuters, called activists’ concerns about the project incorrect and misleading, but added it is open to feedback.

“Such protests are their democratic right. In case any of these claims are legitimate, the government is committed to engaging and providing factual clarifications and suitable redressal,” it said.

Google, in a statement to Reuters, said its project will be developed in line with applicable laws and it will implement “advanced air cooling to protect vital local water resources”.

Read more: Google breaks ground on Indian AI megahub

Work ​was well underway when Reuters visited on ​Monday, earthmovers still working the exposed ⁠ground.

The tech giant has partnered with Indian billionaire Gautam Adani’s group, which will build the marquee project, which is seen creating up to 188,000 jobs. Adani did not respond to queries.

Wildlife and noise pollution

The public interest litigation in Andhra Pradesh High Court ​also raises concerns that heavy construction and noise impact the Kambalakonda Wildlife Sanctuary located just 860 metres away.

Asked about the ​site’s proximity to the ⁠sanctuary, the state said it was farther away than the law requires. Google added it will be implementing sound-dampening measures to ensure “we are a quiet, unobtrusive neighbour.”

The project also faces three more cases filed at India’s environmental court by the Human Rights Forum, demanding a halt. They argue the state cleared the project without properly assessing the impact of drawing ⁠supply from a ​rural drinking-water scheme, court documents show.

Also read: Bombay High Court allows Preity Zinta to pursue deepfake case against Google and Meta

The state added that no water for rural or residential purposes ​will be used for the upcoming data centres, and the water reservoir nearby will also not be used.

During the Sunday event, Green Visakha said it was concerned about the government’s promise of “guaranteed” water supplies for ​20 years to the project as the city already faces shortages.

“Who will be the sufferers? The people,” said Roy.

Source Link